Patel dubs Amazon's Trainium chip the Amazon Basics TPU due to less efficient but cost-effective design.
“Yeah. So so funnily enough, Amazon's chip is the Amazon I I call it the Amazon's basics TPU. Right?”
Patel says Amazon and Anthropic building 400,000 chip Trainium supercomputer proves they believe scaling continues.
“And and because of this, right, Amazon and Anthropic have decided to, you know, make a 400,000 Trainium server supercomputer. Right? 400,000 chips. Right? Going back to the whole scaling law is dead.”
Patel reveals Amazon and Anthropic are building a 400,000 Trainium chip supercomputer as evidence scaling continues.
“Amazon and Anthropic have decided to, you know, make a 400,000 Trainium server supercomputer. Right? 400,000 chips. Right? Going back to the whole scaling law is dead.”
“Tranium, by far. Tranium is going to be to 2026, especially in the second half of this year when Tranium three really ramps, as TPUs were to twenty twenty five.”
Baker argues Trainium is most underestimated because frontier mixture-of-expert models require switched scale-up networks for inference.
“And so Trainium is for sure the most underestimated, not only because of those design choices, but because the all of these frontier models are what are called mixture of expert models.”
Baker states only NVIDIA and Amazon Trainium have functioning switched scale-up networks for inference today.
“And the only two functioning switched scale up networks in the world today are the ones that power NVIDIA GPUs and Amazon's Trainiums.”
Patel reports Trainium rents for under $10 billion per gigawatt while GPUs cost $12-13 billion.
“Tranium sells at sub $10,000,000,000 per gigawatt rental rate to Anthropic and to OpenAI. GPUs, at least before the craziness of the last six months, usually went around 12 to $13,000,000,000 per gigawatt.”